PROCEDURE QUALIFICATION RECORD (PQR)
BASIC
·
PQR is a document which shows that the welders of our
company has a tendency to produce a sound welding which gives proper mechanical
strength and metallurgical properties.
·
PQR is also prepared with a proper standard like ASME
section IX.
·
If the values of testing parameters matches with the
standard values stated in SWPS/WPS then we can say that our procedure is
qualified and with this procedure welder can produce a sound weld.
·
In short the PQR gives an evidence that given WPS can
produce an acceptable or sound weld quality.
·
After completion of WPS (welding procedure
specification) the parameters which are entered into WPS needs to check at
actual.
·
Hence during welding all required parameters are
record in a sheet.
PROCESS OF
PRODUCING PQR
·
We have to make WPS before going to PQR, as already
discussed about WPS.
·
After completion of WPS needs to prepare test coupon
for welding with appropriate dimensions minimum required for testing.
·
Test coupon must be neat and cleaned with proper edge
preparation as per ASME section IX.
·
Tack weld the test coupon with end plates on both end
of the plates with axis of welding.
·
Welding is start in required position of qualification,
all welding positions are described already in another section.
·
Note down the welding parameters during welding that
is current, voltage, travel speed, base metal material, filler metal material
etc. which are already given into WPS.
·
Welding parameters should be as per WPS.
·
Welding should be witnessed by the AWS certified
welding inspector or an inspection body.
·
Once the welding of test coupon is completed it sent
to the Radiography testing (non-destructive testing), in RT weld defects are
identified and witnessed by inspection agency or welding inspector.
·
If RT of weld coupon is acceptable then it sent for
destructive mechanical testing. (Different mechanical testing already discussed
on another section)
·
In destructive testing various testing are carried out
like bend test, tensile test, impact test if requires etc.
·
Also metallurgical testing is done in the NABL qualified
laboratory.
·
Those reports of all testing, RT films review reports
are collected with inspector signature and documented as a supporting to PQR.
·
After completion of all test the surveyor review the
reports, values mention in WPS and actual PQR report if matches within tolerance
limit then he sign the WPS and PQR with his endorsement.
·
After endorsement of welding engineer the WPS is said
as qualified with supporting PQR.
ACCEPTANCE
CRITERIA
·
Weld visual
It is accepted by welding engineer on the basis of
visual testing.
All welding parameters are accepted by predefined WPS.
·
Radiography testing
It is accepted on the basis of film review & ASME
section VIII div 1 appendix 4.
·
Mechanical testing
Mechanical testing acceptance criteria is as per ASME
section IX.
For each testing acceptance criteria is different.
Tension test gives the value for tensile strength and
bend test gives ductility value.
·
Metallurgical testing
It is accepted on the criteria given in the ASME
section II.
It varies with the material of base metals and welding
consumables.
NOTE
·
PQR should include the essential parameters which are
given in the WPS like P number, F number, PWHT etc.
·
PQR also include the supplementary essential
parameters such as Group number of materials.
·
PQR need not contain any non-essential parameters as
per code requirement.
·
For impact testing test coupon must be cut into
required sample pieces.